Ceba Solutions Ltd were asked to transform existing facilities into a brand new health bar and a separate cafe & deli bar for Man Group

Background

Man Group are located in a prestigious building overlooking the Thames in Swan Lane, London.

Challenges

There was a very short turn around period to complete the project for the go-live date. The existing coffee/deli bar had to be stripped out on Friday and the replacement was to be re-instated by Sunday evening. We then had 8 days to complete the health bar.

Solution

Due to the time restraints on the project, Ceba were required to break the project down into two installation periods. We had 6 trades on site at once, with hour by hour coordination to ensure all angles of the works were achieved within the timescale.

Ceba was also responsible for the full strip out of the pre-existing equipment, walls and associated redundant services.

How was it achieved?

Ceba’s project management team ran the program, with regular site visits prior to installation and providing onsite supper during installation. We also consulted with all parties to ensure we could provide the necessary space and equipment to deliver the menu offer. Finally, Ceba worked closely with the catering team to achieve a modern and functional space within their guidelines.

Equipment

We engaged with our service partners to fabricate the counter to our design, incorporating the following equipment:

Coffee Bar

  • Refrigerated patisserie display
  • Display shelving
  • Wipe clean wall paper (Artwork by Ceba)
  • Shelving with LED strips
  • Tiling to both walls and front of counter

Healthy Bar

  • Urban Cultivators
  • Single door under counter refrigeration
  • Hot multideck display
  • Bespoke shelving and racking
  • Self-serve refrigerated multideck
  • Mobile pop up table
  • Shelving with LED lighting strips
  • Artificial green hedging